|
Updated August 6, 2010
Section 1
All work has been completed.
Section 2
Our crews are paving today in Section 2.
Section 3: All work has been completed.
Section 4
Phase 3 - Milling will be 8/16/10 through 8/20/10
Phase 4 - Paving will be 8/23/2010
through 8/27/2010
Town of Perinton
2010 Capital Road Construction – Complete Reconstruction
Tentative Schedule |
|
Work Description |
Road Construction
(Streets are listed in the order that work will occur) |
|
|
|
Section 1 |
Section 2 |
|
Bayberry Circle, Dahlia Drive, Gentian Way, Larkspur Lane, Mulberry Circle
|
Golf Stream Drive, Hilltop Drive, Putting Green Lane |
|
Section 3 |
Section 4 |
|
Eaglesfield Way, Killeen Drive, St. Andrews Blvd.
Total Length: 6.54 miles |
Broken Hill Road, Cabernet Circle, Chablis Drive, Claret Drive, Emerald Hill Circle, Foxboro Lane, Whisperwood Drive |
|
|
Phase I
Drainage Inlet Repair |
Section 1: Complete
Section 3: N/A |
|
|
|
Section 2: April 5, 2010 through April 30, 2010
Section 4: N/A |
|
|
|
|
Phase II
Concrete Gutter Repair |
Section 1: May 3, 2010 through May 31, 2010
Section 3: June 18, 2010 through July 16, 2010 |
|
|
|
Section 2: June 18, 2010 through July 16, 2010
Section 4: June 28, 2010 through July 23, 2010 |
|
|
|
|
Phase III
Road Milling |
Section 1: June 1, 2010 through June 4, 2010
Section 3: July 19, 2010 through July 22, 2010 |
|
|
|
Section 2: July 19, 2010 through July 22, 2010
Section 4: July 26, 2010 through July 30, 2010 |
|
|
|
|
Phase IV
Road Paving |
Section 1: June 14, 2010 through June 18, 2010
Section 3: July 26, 2010 through July 30, 2010 |
|
|
|
Section 2: July 26, 2010 through July 30, 2010
Section 4: Mid-August (please see updates for
further information) |
|
|
|
|
Please Keep In Mind That These Dates Are Tentative. Their Purpose Is To Provide Residents With A General Time Frame For Work To Be Accomplished In Their Respective Neighborhoods. Updated Information And Progress Reports Will Be Available On The Town's Website. You Will Be Notified the Day Before Commencement Of Final Paving. |
|
Town of Perinton Websit
Thomas C. Beck - Commissioner of Public Works 223-5115 James Spencer - Deputy Commissioner of Public Works- Highways 223-5115 |
|
Town of Perinton Supervisor - James E. Smith 223-0770 |